Minutemen Causeway Construction Schedule Update, All Business Open For Business
By Space Coast Daily // June 16, 2016
tentative construction schedule

BREVARD COUNTY • COCOA BEACH, FLORIDA – Below is the tentative construction schedule for the entire Minutemen Causeway project.
The start and finish dates may change due to weather or unforeseen issues.
Please note that all businesses on Minutemen Causeway and Brevard Avenue are open for business during the construction.
Block 2 – Sunset to Brevard Avenue
START: May 5, 2016
FINISH: August 15, 2016
Block 3 – Brevard Avenue – Orlando Avenue
START: June 22, 2016
FINISH: October 3, 2016
Block 4 – Orlando Avenue – AtlanticAvenue
START: October 4, 2016
FINISH: January 17, 2017
Block 5 – Atlantic Avenue – Project end
START: January 18, 2017
FINISH: April 12, 2017
Traffic Signalization
START: May 13, 2016
FINISH: January 11, 2017
Irrigation – Landscape – Hardscape
START: October 17, 2016
FINISH: November 21, 2016
Final Paving
START: January 13, 2017
FINISH: February 27, 2017
CLICK HERE FOR BREVARD COUNTY NEWS