Minutemen Causeway Construction Schedule Update, All Business Open For Business

By  //  June 16, 2016

tentative construction schedule

The City of Melbourne Public Works & Utilities Department will be closing W. Fee Ave in between Glendon Drive and Park Avenue, in Melbourne, in order to repair a sanitary sewer main.
Below is the tentative construction schedule for the entire Minutemen Causeway project. The start and finish dates may change due to weather or unforeseen issues. Please note that all businesses on Minutemen Causeway and Brevard Avenue are open for business during the construction.

BREVARD COUNTY • COCOA BEACH, FLORIDA – Below is the tentative construction schedule for the entire Minutemen Causeway project.

The start and finish dates may change due to weather or unforeseen issues.

Please note that all businesses on Minutemen Causeway and Brevard Avenue are open for business during the construction.

Block 2 – Sunset to Brevard Avenue
START: May 5, 2016
FINISH: August 15, 2016

Block 3 – Brevard Avenue – Orlando Avenue
START: June 22, 2016
FINISH: October 3, 2016

Block 4 – Orlando Avenue – AtlanticAvenue
START: October 4, 2016
FINISH: January 17, 2017

Block 5 – Atlantic Avenue – Project end
START: January 18, 2017
FINISH: April 12, 2017

Traffic Signalization
START: May 13, 2016
FINISH: January 11, 2017

Irrigation – Landscape – Hardscape
START: October 17, 2016
FINISH: November 21, 2016

Final Paving
START: January 13, 2017
FINISH: February 27, 2017

CLICK HERE FOR BREVARD COUNTY NEWS