SEE THE SCHEDULE: State Road 528 Lanes Will Be Shut Down Due to Brightline Construction
By Space Coast Daily // March 4, 2021
two tunnels under S.R. 528 are being constructed
BREVARD COUNTY, FLORIDA – The following closures will be in effect between March 14, 2021, through March 30, 2021 as construction crews build two tunnels under State Road 528 for Brightline.
Eastbound and westbound SR 528 (from Industry Rd. to US-1)
FULL ROAD CLOSURE:
■ 10 p.m., Sunday, March 14 to 5 a.m., Monday, March 15
■ 10 p.m., Monday, March 29 to 5 a.m., Tuesday, March 30
Detour Information:
■ Eastbound SR 528 traffic will be directed to exit at Clearlake Rd. (Exit 45), travel south on Industry Rd. to SR 524, travel east on SR 524/Clearlake Rd. and follow south to SR 520, travel east on SR 520 to US-1 and travel north on US-1 to access eastbound SR 528.
■ Westbound SR 528 traffic will be directed to exit at US-1 (Exit 46), travel south on US-1 to SR 520, travel west on SR 520 to Clearlake Rd., travel north on Clearlake Rd. to Industry Rd. and travel north on Industry Rd. to access westbound SR 528.
■ Eastbound and westbound SR 528 (from Industry Rd. to US-1)
Single lane closure in each direction, 5 a.m., Monday, March 15 through 10 p.m., Monday, March 29.
■ Traffic will be shifted to west side of SR 528 and will be reduced to one lane in each direction. As work progresses, traffic will be shifted from the westbound to the eastbound side of SR-528remaining in one lane in each direction.
RAMP CLOSURES:
Northbound Industry Rd. entrance ramp to eastbound SR 528
Full ramp closure, 10 p.m., Sunday, March 14 to 5 a.m., Tuesday, March 30.
Detour Information:
■ Northbound Industry Rd. traffic wishing to travel east on SR 528 will be directed to travel south on Industry Rd. to SR 524, travel east on SR 524 to Clearlake Rd., travel south on Clearlake Rd. to SR 520, travel east on SR 520 to US-1 and travel north on US-1 to access eastbound SR 528.
■ Northbound US-1 entrance ramp to westbound SR 528
Full ramp closure, 10 p.m., Sunday, March 14 to 5 a.m., Tuesday, March 30.
Detour Information:
■ Northbound US-1 traffic wising to travel west on SR 528 will be directed to travel south on US-1 to SR 520, travel west on SR 520 to Clearlake Rd., travel north on Clearlake Rd. to Industry Rd. and travel north on Industry Rd. to access westbound SR 528.
■ Eastbound SR 528 exit ramp to northbound US-1 (Exit 46)
Full ramp closure, 10 p.m., Sunday, March 14 to 5 a.m., Tuesday, March 30.
Detour Information:
■ Eastbound SR 528 traffic wishing to travel north on US-1 will be directed to exit early at Industry Rd./Clearlake Rd. (Exit 45), travel south on Industry Rd. to SR 524, travel east on SR 524 to Clearlake Rd., travel south on Clearlake Rd. to SR 520, travel east on SR 520 to US-1 and travel north on US-1 to access eastbound SR 528.