Immediate Recovery Operations Following Sewer Force Main Break in Palm Bay Now Complete
By Space Coast Daily // June 18, 2025
City od Palm Bay will continue regular water quality testing and environmental monitoring

3.19 Million Gallons of Wastewater Released Due to Sewer Force Main Break in Palm Bay
BREVARD COUNTY • PALM BAY, FLORIDA — The City of Palm Bay has completed immediate on-site recovery operations following the sewer forcemain break near 1050 Clearmont Street NE.
As part of final restoration efforts, 54 pallets of sod were delivered and installed to restore the impacted pond system and right-of-way areas.
Crews have successfully removed all turbidity barriers and flock logs from Turkey Creek, and active aeration of the water continues to support the ecosystem’s natural recovery.
Contaminated materials have been removed to the greatest extent possible, and final roadway cleaning and repairs are scheduled for Tuesday, June 17, which marks the final day of on-site recovery operations. However, this does not mark the end of our commitment.
The City will continue regular water quality testing and environmental monitoring to ensure the ongoing safety of the area for residents and wildlife.
We appreciate the community’s patience and understanding throughout this process. Further updates will be shared as necessary through official City channels.

Approximately 2 million gallons have been recovered through ongoing remediation efforts, with an estimated 1.19 million gallons released into the environment.
Following the successful repair and containment of the sewer forcemain break near 1050 Clearmont Street NE, further investigation has revealed the cause of the failure.
According to Palm Bay city officials, the damaged section, a 20-foot-long pipe, was found to have a 2- to 3-inch crack running the full horizontal length.
Although the pipe was originally expected to have a lifespan of 80-100 years, it failed after just 37 years, or half its lifespan.
Palm Bay city officials said this break could not have been reasonably anticipated, as routine inspections of the collection system are conducted monthly. The last inspection of the air release valve was completed two weeks prior.
Additionally, pressure data loggers are being monitored routinely for increased demand, indicating stress on the system.

Upon excavation, it was discovered that the pipe had been installed at an unusual angle, which may have contributed to long-term strain and ultimately led to the failure.
Importantly, the issue does not appear to be related to overcapacity in the area, as that portion of the system does not serve a zone currently impacted by growth.
At this time, preliminary estimates indicate that approximately 3.19 million gallons of wastewater were released as a result of the break.
Of that, approximately 2 million gallons have been recovered through ongoing remediation efforts, with an estimated 1.19 million gallons released into the environment.
“The City remains committed to full transparency and will continue to provide updates as environmental remediation and water quality monitoring continue. Further updates will be provided as needed,” said a City of Palm Bay spokesperson.
The citizen hotline 321-726-5683 will have the most current information.















