NASA’s Artemis I Team Adjusts Dates for Cryogenic Demonstration Test, Next Launch Opportunity Now Sept. 27

By  //  September 15, 2022

NASA engineers will conduct the demonstration test no earlier than Wednesday, Sept. 21

NASA Engineers are making progress repairing the area where a liquid hydrogen leak was detected during the Artemis I launch attempt Sept. 3, and NASA is preserving options for the next launch opportunity as early as Tuesday, Sept. 27. (NASA image)

BREVARD COUNTY • KENNEDY SPACE CENTER, FLORIDA – NASA Engineers are making progress repairing the area where a liquid hydrogen leak was detected during the Artemis I launch attempt Sept. 3, and NASA is preserving options for the next launch opportunity as early as Tuesday, Sept. 27.

NASA has adjusted the targeted dates for a cryogenic demonstration test and the next launch opportunities for Artemis I, the first integrated flight test of the Space Launch System rocket and Orion spacecraft beyond the Moon.

The agency will conduct the demonstration test no earlier than Wednesday, Sept. 21, and has updated its request for a launch opportunity on Sept. 27, with a potential backup opportunity of Oct. 2 under review.

The updated dates represent careful consideration of multiple logistical topics, including the additional value of having more time to prepare for the cryogenic demonstration test, and subsequently more time to prepare for the launch.The dates also allow managers to ensure teams have enough rest and to replenish supplies of cryogenic propellants.

NASA and SpaceX also continue to target no earlier than 12:45 p.m. EDT Monday, Oct. 3, for the launch of the agency’s Crew-5 mission to the International Space Station.

Teams are working on the upcoming commercial crew launch in parallel to the Artemis I planning and both launch schedules will continue to be assessed over the coming weeks. NASA and SpaceX will review the Artemis I and Crew-5 prelaunch processing milestones to understand any potential impacts. The agency’s Crew-4 return will continue to be planned following a short handover on the space station with Crew-5.

The SLS rocket and Orion spacecraft are in good condition while remaining at the launch pad. Technicians constructed a tent-like enclosure around the work area to protect the hardware and teams from weather and other environmental conditions at Launch Pad 39B. (NASA image)

Last weekend, Artemis I teams completed repair work to the area of a hydrogen leak, reconnecting the ground- and rocket-side plates on the quick disconnect for the liquid hydrogen fuel feed line where two seals were replaced last week.

This week teams are conducting tests at ambient conditions to ensure there is a tight bond between the two plates before testing again during the cryogenic tanking demonstration and begin preparations for the test.

During the demonstration, launch controllers will load supercold liquid oxygen and liquid hydrogen into the core stage and interim cryogenic propulsion stage of the SLS rocket. The demonstration will allow teams to confirm the hydrogen leak has been repaired, evaluate updated propellant loading procedures designed to reduce thermal and pressure-related stress on the system, conduct a kick-start bleed test, and evaluate pre-pressurization procedures.

NASA is continuing to respect the Eastern Range’s process for review of the agency’s request for an extension of the current testing requirement for the flight termination system and is providing additional information and data as needed. In parallel, the agency is continuing preparations for the cryogenic demonstration test and potential launch opportunities, should the request be approved.

Specific times for the potential launch opportunities are as follows:

Sept 27: 70-minute launch window opens at 11:37 a.m. EDT; landing on Nov. 5
Under review – Oct. 2: 109-minute launch window opens at 2:52 p.m.; landing on Nov. 11

NASA’s teams internally are preparing to support additional dates in the event flexibility is required. The agency will evaluate and adjust launch opportunities and alternate dates based on progress at the pad and to align with other planned activities, including DART’s planned impact with an asteroid, the west coast launch of a government payload, and the launch of Crew-5 to the International Space Station.